# Basketball court reconstruction

Federal contract opportunity, via Kontrakk.

- **Agency:** STATE, DEPARTMENT OF.STATE, DEPARTMENT OF.US EMBASSY VIENNA
- **Notice ID:** 315bd0cf47be4a308e31a8c0bf41d86c
- **Solicitation number:** 19AU9026Q0010
- **Notice type:** Presolicitation
- **NAICS:** 238990
- **Place of performance:** Vienna, AT-9
- **Posted:** June 11, 2026
- **Response deadline:** July 29, 2026
- **View on Kontrakk:** https://kontrakk.com/contracts/315bd0cf47be4a308e31a8c0bf41d86c
- **View on SAM.gov:** https://sam.gov/workspace/contract/opp/315bd0cf47be4a308e31a8c0bf41d86c/view

## Description

This project if for the reconstruction of the basketball half-court at the U.S. Embassy Vienna Marine House, located in 1190 Vienna.

The existing outdoor basketball half-court is at the end of its life cycle and too small in dimensions.

The scope of work includes but is not limited to the demolition of the existing sports field surface and substructure, in their entirety, as well as the removal of the lighting.

Construction of a new sports field surface, including the substructure, in its entirety, as well as a new lighting system.

Scope of work: General Contractor for Construction of Sport Fields and Electrical Installation

- Site Installation

- Demolition

 
Demolition, removal and disposal of existing basketball half- court (asphalt layer 7x8m), existing exterior lights and basketball basket with posts 

 
Soil removal and disposal for new basketball half- court dimension (13mx14m = 182m&sup2;), 0.3m depth = ~55m&sup3;

- Construction of a new sport field

 
Preparation/installation subgrade/subbase incl. drainage

 
Installation top layer (EPDM rubber surface or equal)

 
Installation point foundation for 1 basketball hoop and for 2 light poles

 
Installation 1 adjustable basketball hoop, and 2 exterior lights incl. cabling/rewiring

 
Laying stone slabs 40x40x5cm around the court

 
Painting lines

 
Final cleaning

- Special requirements

 
The work will be carried out while the facility remains in operation and in the presence of the residents, who should not be disturbed during the construction work

 
USG Security regulations

 
Clearance process for employees, cars, material on site

 
Safety and protective measures

Execution periods

Indicative construction schedule: 5 weeks in fall 2026

## Points of contact

- Zahid Raja · rajazm@state.gov (primary)
- Daniel Worel · woreld@state.gov (secondary)